Joint and several liability withdrawn

So ruled the Supreme Court in its resolution dated 10 July 2015 (ref. no III CZP 45/15).

In its resolution, the Supreme Court confirmed that in the event of rescission by the contractor of construction contract concluded with the subcontractor, the investor will not bear joint and several liability with the contractor for payment of remuneration of subcontractor pursuant to art. 6471 § 5 of the Civil Code.